Montgomery County · Upper Frederick · MCPC #26-0290-001
Frederick Living Apartment Project
2849 BIG ROAD, Upper Frederick, PA · 73 homes, apartments · 69.7 acres
In short: Frederick Living Apartment Project is an apartment development at 2849 Big Road in Upper Frederick, Montgomery County, PA. It would add 73 homes on 69.7 acres. Its estimated construction value is about $17.5M, a rough estimate from its size. As of November 24, 2026, it is in review. Latest record: Land dev plan, prelim plan sent to the county planning commission for review (November 13, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
Frederick Living, a retirement community on Big Road in Upper Frederick Township, is expanding its campus with new apartment buildings, including a 45-unit apartment building, a 16-unit set of garden apartments, and a 12-unit hybrid building. The project totals 73 homes on a roughly 69.7-acre tract, with about 11 acres affected by the work. Stormwater will be handled by a new detention and bioretention basin, and sewer and water will remain on the campus's existing private systems.
Issues raised: Ground-floor unit count exceeds six-unit multifamily definition, Private ownership and maintenance agreements for sewer, water, and stormwater, Compliance documentation for existing private water and sewer systems, Lot consolidation reference needed clarification, Environmental assessment statement determination, Zone boundary display on Sheet LD-5
- Applicant
- Frederick Living
- Engineer / rep.
- RGS Associates
- Zoning
- R-40
- Tax parcel
- 55-00-00298-00-7
- Cross street
- Heimbach Road
- Approvals needed
- waivers, conditional use, lot line change
- Utilities
- private wells, private wastewater system
Project history
- 2026-11-13 · MCPC #26-0290-001 · Land Dev Plan, Prelim Plan · 73 homes
The full picture AI research · Nov 21, 2026
Frederick Living is a retirement community on Big Road in Upper Frederick Township. County records show it plans to add 73 apartments to its existing campus. The plan has three parts: a 45-unit apartment building, a 16-unit set of garden apartments, and a 12-unit building that mixes housing types. The campus covers about 69.7 acres, and the construction would disturb about 11 of them.
Rainwater would drain to a new detention and bioretention basin. These are shallow basins that hold stormwater and release it slowly. Sewer and water would stay on the campus's existing private systems.
The county filing from 2026-11-13 shows the preliminary plan was sent to the county planning commission for review. Web searches found no news coverage, township agenda or minutes, opposition, listings, or construction announcements for these apartments. The searches did confirm that Frederick Living already offers apartments for ages 55 and up on this campus.
What it could mean nearby
- The new homes would sit inside an existing retirement campus, so they add housing without a new neighborhood.
- Stormwater would be managed by a new on-site basin, and the records say about 11 acres would be disturbed.
- Water and sewer would stay on the campus's private systems, so the records point to no new public utility connections.
- No traffic study, school effect, or job numbers were found in the sources reviewed.
Where it stands
The preliminary land development plan is under review. It was sent to the county planning commission on 2026-11-13. Review comments and township decisions usually follow, and a final plan approval comes before any building permits.
- Nov 13, 2026 Preliminary land development plan sent to the county planning commission for review
Who's behind it
Frederick Living · A retirement community (continuing care) in Upper Frederick, PA. It offers apartments for ages 55 and up, and a contractor's project page says it has also added independent-living cottages.
Around the web
- Oaktree ApartmentsFrederick LivingShows Frederick Living already offers apartments for ages 55 and up on its campus. The page itself could not be opened, so this comes from the search result.
- Wagman's Renovation Transforms Dining Experience at Frederick LivingWagman ConstructionShows earlier campus work by a contractor. It does not mention the new apartments. This comes from the search result only.
Planning terms explained
- Land development plan
- A detailed site plan showing the buildings, roads, utilities and stormwater controls for a project, which the township must approve.
- Preliminary plan
- An early formal version of the plan that is reviewed and revised before the final plan is approved.
- County planning commission
- A county body that reviews local plans and sends non-binding comments to the township.
- Bioretention basin
- A planted, shallow basin that collects runoff and lets it soak into the ground slowly.
- Detention basin
- A basin that temporarily holds stormwater and releases it gradually to reduce flooding downstream.
Researched by AI from public sources on Nov 21, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Upper Frederick Township planning commission and board of supervisors handle local review of land development plans, and residents can usually comment at their public meetings. The township's website lists meeting dates.
In Pennsylvania, Upper Frederick decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Upper Frederick planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Upper Frederick manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Upper Frederick's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
From the filings read by AI
- 73 apartments
- 11.0 acres disturbed
- Stormwater: detention basin/bioretention facility
- Sewer: pump station
- Water: private well
Trades: sitework, utilities, stormwater
Estimated construction value: $17.5M
- ~438 roofing squares
- ~73 HVAC systems
- ~73 kitchens / 146+ bathrooms
- ~73,000 sq ft of finished living space
- ~11.0 acres of site work (grading, stormwater, landscaping)
- New detention basin and bioretention facility
- Relocation of a portion of the dry fire line
- New sanitary sewer connections to existing pump stations
- Fire hydrant and FDC location improvements
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Blantyre North and South0.3 mi · 278 homes, townhomes · Upper Frederick · filed 2025-01-28
- Township Line Road Reverse Subdivision0.5 mi · lot line change · Upper Frederick · filed 2025-07-30
- 429 Fagleysville Road0.9 mi · 2 homes, single family · Upper Frederick · filed 2025-10-21
- 565 Hildebrandt Road2.0 mi · lot line change · New Hanover · filed 2026-01-14
- 225 Big Road2.4 mi · 29 homes, single family · Lower Frederick · filed 2025-08-19
- Lot line change on Gravel Pike2.4 mi · lot line change · Upper Frederick · filed 2025-07-17