Carbon County · Franklin Township · #3960
Market Hill Estates major subdivision
Franklin Township, PA · subdivision (use not stated)
In short: Market Hill Estates major subdivision is a subdivision in Franklin Township, Carbon County, PA. As of November 24, 2026, it is in review. Latest record: Board of Supervisors: final plan (August 18, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.
Usually next: a planning commission recommendation, then a vote by the town's governing body.
About this project
A major subdivision in Franklin Township submitted by Cedar Creek Realty Investments as owner and developer, at the final plan stage. The agenda does not describe the number of lots, the acreage, or what is on the land now.
- Applicant
- Cedar Creek Realty Investments
- Plan type
- Final major subdivision
- Land use
- other
Project history
- 2026-08-18 · Board of Supervisors · Final plan · source
- 2024-10-15 · #3960 · Final major subdivision
Map pin is approximate.
The full picture AI research · Nov 15, 2026
Market Hill Estates is a proposed 18-lot subdivision on about 6.8 acres in Franklin Township, Carbon County. It sits at Market Street and Long Run Road in a residential zone. Cedar Creek Realty Investments is listed in county records as owner and developer. Local news calls the company Cedar Realty Investment LLC. One lot is meant for a stormwater basin and the rest for single-family houses. The county filing does not say what is on the land now.
The plan is not new. It got conditional preliminary approval in 2007. When the county planning commission reviewed it in October 2024, it did not recommend approval as submitted. It listed 69 items to fix, including a highway permit and sewage, stormwater and erosion plans. In December 2025 the township supervisors extended the project's deadline to June 30, 2026.
No builder page, home listings or construction news were found, so nothing shows work on the ground.
What it could mean nearby
- Up to 17 single-family house lots could add homes at Market Street and Long Run Road. This comes from a news report of the plan.
- The county review required a highway occupancy permit, so road access and traffic are open issues.
- A stormwater basin is planned on one lot, and the review also requires sewage and water connection details.
Where it stands
The county records show the final plan for the Board of Supervisors dated 2026-08-18, and no decision on it was found. If the supervisors approve it, the developer must still meet conditions and get permits before building.
- Aug 18, 2026 Board of Supervisors: final plan on the records
- Jun 30, 2026 Deadline set by the supervisors' extension, which has since passed
- Dec 2025 Township supervisors approved an extension for the project
- Oct 15, 2024 County planning commission reviewed the plan and did not recommend approval as submitted
- 2007 Conditional preliminary plan approval, per local news
Who's behind it
Cedar Creek Realty Investments · The company is the owner and developer on the filing. A news report names it Cedar Realty Investment LLC, and no company website or other projects were found.
Around the web
- County planning commission review of Market Hill EstatesTimes News (tnonline.com) · Oct 19, 2024Gives the 18 lots, 6.79 acres and location. It also reports the 2007 conditional approval and the 69 deficiencies the county listed.
- Market Hill extensionTimes News (tnonline.com) · Dec 24, 2025Reports that the supervisors approved an extension to June 30, 2026.
- Franklin Township Board of Supervisors document (2026-08-18 final plan)Franklin Township, Carbon County · Aug 18, 2026This is the county-listed record for the final plan review. Its text could not be read here, so it was used only as the listed record.
Planning terms explained
- Major subdivision
- A division of land into several lots that needs formal plan approval by the township.
- Preliminary plan
- The first detailed plan stage, where the township and county review the layout and engineering.
- Final plan
- The last plan stage, where supervisors give the approval that lets lots be recorded.
- Highway occupancy permit
- A state or local permit for connecting a new driveway or street to a public road.
- Stormwater detention basin
- A designed basin that holds runoff after storms and releases it slowly.
Researched by AI from public sources on Nov 15, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: The Franklin Township Board of Supervisors takes the final action on the plan, and residents can comment at its public meetings or by contacting the township office.
In Pennsylvania, Franklin Township decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.
- Speak at the Franklin Township planning commission or governing body (board of supervisors or council) meeting when the plan is on the agenda. Public comment there goes on the official record.
- Or email or mail a written comment to the Franklin Township manager or zoning officer, name the plan and its address, and ask that your comment be entered into the record.
Find Franklin Township's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Revised Eagle Hospitality land development, Franklinsame area · retail & commercial · Franklin Township · filed 2025-03-18
- Minor subdivision in Franklin Townshipsame area · subdivision (use not stated) · Franklin Township · filed 2026-07-21
- Lot combination, Franklin Townshipsame area · lot line change · Franklin Township · filed 2025-10-21
- Minor subdivision/lot combination, Franklin Townshipsame area · lot line change · Franklin Township · filed 2026-11-17
- Minor subdivision on Long Run, Franklin Townshipsame area · subdivision (use not stated) · Franklin Township · filed 2025-02-18
- Eagle Hospitality land development, Franklin Twpsame area · institutional · Franklin Township · filed 2025-03-18