Centre County · State College Borough · #PAD140129
Penn State Pollock Halls
State College Borough, PA · institutional
In short: Penn State Pollock Halls is an institutional project in State College Borough, Centre County, PA. As of November 24, 2026, it is under construction according to web research. Latest record: Penn State's May 2026 news story says plumbing and framing are done and tile work is under way in Wolf and Ritner halls, with reopening planned for August 2026. What usually happens next: completion and occupancy.
Usually next: completion and occupancy.
About this project
Penn State project at Pollock Halls in State College Borough, Centre County, filed for a DEP construction stormwater permit.
- Applicant
- THE PA STATE UNIV
- Plan type
- Construction stormwater permit (DEP)
- Land use
- Commercial or industrial
- Status
- Site active
The full picture AI research · Nov 6, 2026
Penn State is renovating the Pollock Halls residence hall complex at University Park, in State College Borough. The complex has nine student housing buildings from the 1960s. The university chose to rebuild the insides of the existing buildings rather than tear them down. The work is split into phases.
Phase 1 covers Wolf and Ritner halls. It adds climate control, better accessibility, upgraded study and laundry rooms, community kitchens, shared bathrooms on each floor and more lounge space. Penn State said in May 2026 that this phase was nearly done and on schedule to reopen for the fall 2026 semester. The state stormwater permit in the county records is tied to this kind of site work.
Later phases cover Hiester and Shulze, then the other halls, with the whole complex expected to finish in fall 2030. No opposition was found. Penn State will use the halls for student housing.
What it could mean nearby
- Construction activity continues around Pollock Road and the Pollock complex through about 2030, as the phases move from hall to hall.
- Housing capacity at Pollock drops while halls are closed in turn, then returns as each phase reopens.
- The work is on existing buildings, so no new neighborhood housing or large new footprint is shown in the sources.
Where it stands
Work is past the permit stage. The state stormwater permit was issued May 19, 2025, and Penn State said in May 2026 that the first phase was nearing completion for a fall 2026 reopening. Later phases follow one after another through 2030.
- Sep 2030 Full Pollock renovation expected to finish (fall 2030)
- Aug 2026 Wolf and Ritner halls scheduled to reopen for students (completion not confirmed in sources found)
- May 2026 Penn State reports first phase nearing completion; Hiester and Shulze phase begins
- May 19, 2025 State construction stormwater permit issued
- Feb 2025 Penn State trustees approve the $92.1 million first phase
- Jan 16, 2025 Latest county filing for the stormwater permit
Who's behind it
The Pennsylvania State University · Penn State is the public research university that owns and operates the Pollock Halls; it is using a design-build team led by Clayco, with Mackey Mitchell Architects and DLA+ Architecture.
Around the web
- First phase of Pollock Halls renovation nears completionPenn State News · May 7, 2026Wolf and Ritner halls were nearly done and on schedule for August 2026, with full completion in fall 2030.
- Penn State trustee committee approves $92M first phase of Pollock Halls renovationsStateCollege.comThe first phase budget is $92.1 million and covers Wolf and Ritner halls.
- Penn State moving forward with $80M second phase of Pollock Hall renovationsStateCollege.comThe second phase, Hiester and Shulze halls, was approved at $79.8 million.
- Pollock Halls Renovation: Ritner Hall and Wolf HallPenn State Office of Physical PlantPenn State's project page for the first phase, which lists the design team and construction manager.
- Penn State Pollock HallsClaycoThe builder describes a five-phase, nine-building renovation of Pollock.
Planning terms explained
- NPDES / construction stormwater permit
- A state permit required when building work disturbs an acre or more of land, to control muddy runoff.
- Design-build
- A method where one team handles both the design and the construction of a project.
- Land development plan
- A site plan the municipality reviews for buildings, parking and drainage.
- Phase
- One stage of a multi-part project, built and opened in sequence.
Researched by AI from public sources on Nov 6, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.
How to comment officially
For this project: Penn State's Board of Trustees funds the phases, and State College Borough's planning commission and council review related site plans in public meetings, where residents can comment.
This is a state stormwater construction permit (NPDES) from the Pennsylvania Department of Environmental Protection. The building plans themselves are decided by State College Borough.
- DEP lists permit applications in the Pennsylvania Bulletin, usually with a 30-day window for written comments to the DEP regional office named in the notice.
- For the project itself, speak at a State College Borough planning commission or governing body meeting when the plan is on the agenda.
Find State College Borough's meeting agendas →
Comments on this page are not sent to officials and are not part of the public record.
What neighbors think
Loading…
Scope estimate for contractors
Not enough detail to estimate.
Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →
More projects nearby
- Hastings & University Student Housing Facility0.5 mi · apartments · State College Borough · filed 2025-11-25
- Westerly & Easterly Parkway0.9 mi · recreation · State College Borough · filed 2024-08-15
- The Retreat At Westerly1.3 mi · industrial · State College Borough · filed 2025-01-21
- Centre Hills Country Club2.1 mi · recreation · State College Borough · filed 2026-03-04
- Clearwater Conservation Center2.5 mi · institutional · College Township · filed 2024-07-16
- Proposed Stack-N-Stor3.2 mi · warehouse & storage · Ferguson Township · filed 2024-04-08