In short: Data center redevelopment is a data center project at 159 Princeton Hightstown Rd in East Windsor Township, Mercer County, NJ. As of November 24, 2026, it is approved according to web research. Latest record: A local news headline says the second QTS data center received a green light from the East Windsor Planning Board, and the Baxtel listing says the board… What usually happens next: building and stormwater permits; site work often starts within 3 to 12 months.

Approved A local news headline says the second QTS data center received a green light from the East Windsor Planning Board, and the Baxtel listing says the board approved the application in May 2026. · web research checked Nov 11, 2026 · source AI research
  1. Proposed
  2. In reviewMay 2025
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: building and stormwater permits; site work often starts within 3 to 12 months.

About this project

Proposes redeveloping 159 Princeton-Hightstown Road in East Windsor Township with a new data center, parking, access roads, and stormwater and utility infrastructure, affecting wetlands and a flood hazard area.

Official description: Proposes redeveloping the site with a new data center, parking, access roads, and stormwater and utility infrastructure, with wetland and flood hazard area impacts requiring a Flood Hazard Individual Permit and related approvals.

Applicant
Qts Investment Properties Princeton LLC
Plan type
State environmental permit application (NJDEP)
Land use
Data center
Status
approved

Project history

  • 2025-11-07 · #1101-10-0002.5 · State environmental permit application (NJDEP)
  • 2025-11-07 · NJDEP freshwater wetlands permit 1101-10-0002.5: approved · source
  • 2025-11-06 · NJDEP freshwater wetlands permit 1101-10-0002.5: issued · source
  • 2025-05-29 · NJDEP freshwater wetlands permit 1101-10-0002.5: application filed · source

County plan review office →

The full picture AI research · Nov 11, 2026

QTS already runs a large data center on its 194-acre former corporate campus at 159 Princeton-Hightstown Road. The county record covers a redevelopment of the site with a new data center, parking, access roads, and stormwater and utility work. It would affect wetlands and a flood hazard area.

Online sources show the company wants a second data center beside the first. One news report describes a two-story building of about 272,000 square feet and 77 feet tall. Neighbors packed several planning board hearings in spring 2026 and raised concerns about power demand, noise, size and electricity rates.

The East Windsor Planning Board approved the second building in May 2026 after three hearings, according to a local news headline and a data-center directory. One report says the approval carried 32 conditions. The state wetlands permit was issued in November 2025. No source confirms that construction has started on the second building.

What it could mean nearby

Where it stands

The state wetlands permit was issued and approved in November 2025, and the township planning board reportedly approved the project in May 2026. Construction permits and a construction start have not been confirmed. Those steps usually follow, along with any remaining utility and state approvals. Note: Baxtel labels the second building as 'under construction' with a 2028 planned year, but no builder, township or news source found shows work has actually started, so approval is the furthest stage clearly supported.

Who's behind it

QTS Investment Properties Princeton LLC (QTS Data Centers) · QTS is a data center company that operates and builds large facilities in several US markets, including the existing East Windsor campus.

Around the web

Planning terms explained
Freshwater wetlands permit
A New Jersey state permit that allows building in or near wetlands under set conditions.
Flood hazard area
Land near a waterway that can flood, where state rules limit and condition construction.
Planning board
The local board that reviews site plans and decides whether they meet township rules.
Substation
A facility that steps down high-voltage power so a large building can use it.
Critical power capacity
The electricity a data center can reliably supply to its computer equipment.

Researched by AI from public sources on Nov 11, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: The East Windsor Township Planning Board has already heard public comment at its spring 2026 hearings. Residents can check the township's planning board agendas and minutes for any further steps.

In New Jersey, the East Windsor Township planning board or zoning board of adjustment decides at a public hearing. Nearby property owners are notified by mail, and the hearing is advertised.

Find East Windsor Township's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Not enough detail to estimate.