Professional office building, Pine Grove Borough

Along Conrad Richter Drive and Mill Street, Pine Grove Borough, PA · 1,500 sq ft non-residential, office

In short: Professional office building, Pine Grove Borough is an office development in Pine Grove Borough, Schuylkill County, PA. It would add 1,500 sq ft of non-residential space. Its estimated construction value is about $450K, a rough estimate from its size. As of November 24, 2026, it is in review. Latest record: Major final land development plan (combined preliminary/final) reviewed at a meeting of the county planning commission (August 12, 2026). What usually happens next: a planning commission recommendation, then a vote by the town's governing body.

In review Major final land development plan (combined preliminary/final) reviewed at a meeting of the county planning commission · Aug 12, 2026 · source
  1. Proposed
  2. In reviewJun 2026
  3. Approved
  4. Permitted
  5. Under construction
  6. Completed

Usually next: a planning commission recommendation, then a vote by the town's governing body.

About this project

Builds a 1,500 sq ft professional office building with an attached 1,500 sq ft garage on an existing parcel in Pine Grove Borough. The plan connects to public water and sanitary sewer. County staff recommends conditional final approval, pending stormwater basin waivers and required bonding and development documents.

County recommendation: Supports, with comments

Issues raised: Stormwater basin waivers needed for freeboard, setbacks, riser, spillway, berm width and bottom slope, Separate waiver letter required for Planning Commission, Development statement and cost estimate required, Financial security and development agreement required, Sidewalk waiver requested (Sec. 1125)

Applicant
Mach-One Realty, LLC
Engineer / designer
HNT, LLC
Plan type
Major final land development plan (combined preliminary/final)
Land use
office
Zoning
CR - Conservation Residential (county report also cites R-3 High Density Residential)

Project history

  • 2026-08-12 · #2026-08-professional-office-building-pine-grove · Major final land development plan (combined preliminary/final) · 1,500 sq ft
  • 2026-06-10 · #2026-06-professional-office-building-pine-grove · Major final land development (preliminary and final combined) · 1,500 sq ft

County plan review office →

Map pin is approximate.

The full picture AI research · Nov 23, 2026

The developer proposes a 1,500 sq ft professional office building with an attached 1,500 sq ft garage. It would sit on an existing parcel in Pine Grove Borough, along Conrad Richter Drive and Mill Street. It would connect to public water and sewer.

The plan has been reviewed twice by the county planning commission, in June and August 2026. County staff recommended conditional final approval. The conditions are waivers for the stormwater basin and the required bonding and development paperwork.

No developer website, news story, borough minutes, listing, tenant announcement or construction notice was found for this site. What is on the ground today could not be confirmed from public sources.

What it could mean nearby

Where it stands

The county planning commission reviewed the combined preliminary/final land development plan on 2026-08-12, and staff recommended conditional final approval. Next come the borough's own decision on the plan, then completion of the bonding and development documents, and later building permits.

Who's behind it

Mach-One Realty, LLC (with HNT, LLC) · Both companies are named on the county filing. No official website or information on their other projects was found.

Around the web

Planning terms explained
Land development plan
A site plan showing a new building, parking, utilities and drainage on a parcel, which the municipality must approve.
Combined preliminary/final plan
A single review that covers both the early and the final approval steps.
Stormwater basin waiver
Permission to skip or change a standard rule about the basin that holds back rainwater runoff.
Bonding
A financial guarantee that the developer will finish required site improvements.
Conditional final approval
Approval that takes effect only after listed conditions are met.

We searched the web for this project but found nothing beyond the county record, so this explanation is based on the filing alone. Researched by AI from public sources on Nov 23, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

How to comment officially

For this project: Pine Grove Borough's governing body and planning officials handle local approval of the plan. Residents can contact the borough office or attend its public meetings, but no specific hearing date was found.

In Pennsylvania, Pine Grove Borough decides on this plan, not the county. The county planning commission only reviews it and sends recommendations.

Find Pine Grove Borough's meeting agendas →

Comments on this page are not sent to officials and are not part of the public record.

What neighbors think

Loading…

Scope estimate for contractors

Estimated construction value: $450K

Contractor or supplier? Get projects like this in the counties you work, by email. Get free contractor alerts →

More projects nearby