PlannedNearby

Montgomery County · Cheltenham · MCPC #25-0085-001

Cedarbrook Middle School - Building Additions & Renovations

300 Longfellow Road, Cheltenham, PA · 18,972 sq ft non-residential, school · 34.11 acres

About this project

The Cheltenham School District plans two additions to Cedarbrook Middle School at 300 Longfellow Road in Wyncote, totaling about 18,972 square feet. The project also reconfigures the parking lots, adds one parking space, and upgrades two underground stormwater beds. Some driveway and pavement areas will be removed, so impervious coverage grows by only about 13,330 square feet.

County planning commission: Supports, with comments

Issues raised: 14 hawthorn trees with thorns proposed near a middle school, Parking island landscaping should be consistent across the full island, Shrub replacement recommended near the northwest entrance and stormwater bed UG2, Tree planting detail needed for slopes along the ball field drive aisle, Stormwater management must handle the added 13,330 sq ft of impervious coverage; county defers to the township engineer

Engineer / rep.
Chester Valley Engineers, Inc.
Zoning
C-2
Approvals needed
waiver from Cheltenham Township Subdivision and Land Development Ordinance Section 260-15c(11)(b)
Utilities
public water (Aqua PA)
Demolition
Some existing driveway and pavement areas removed

Filing history

  • 2025-04-17 · MCPC #25-0085-001 · Land Dev Plan, Prelim Plan · 18,972 sq ft

County review letters
2025-04-17 · CHELT 25-0085-001r.pdf

View all filings on the county site →

The full picture AI research · Nov 1, 2026

The Cheltenham School District plans two additions to Cedarbrook Middle School on Longfellow Road in Wyncote, adding about 18,972 square feet in total. The school sits on a campus of roughly 34 acres. The current building opened in 2018, after the earlier school was closed because of mold.

The work also reshuffles the parking lots, adds one parking space, and upgrades two underground stormwater beds. Some driveway and pavement will be removed, so hard surfaces grow by only about 13,330 square feet.

The additions are tied to a district plan to move to K–5 and 6–8 schools. A May 2025 news report said the additions would provide 19 classrooms for sixth graders. It said construction was expected to start in 2026 and finish by fall 2027. Sixth graders will use temporary modular classrooms in the meantime.

What it could mean nearby

Where it stands

The county planning filing was dated April 2025, and a news report said the school board approved the wider grade-reconfiguration plan in May 2025. Next usually come local land-development and stormwater approvals, bidding, and then construction. Construction was expected to start in 2026, but no confirmation of that was found.

Want to weigh in? The Cheltenham School District board and the Cheltenham Township officials who review land development decide next, and residents can comment at their public meetings.

Who's behind it

Cheltenham School District · The public school district serving Cheltenham Township, which is the project owner. Chester Valley Engineers, Inc. is the engineering firm on the county filing.

Around the web

Planning terms explained
Impervious coverage
Surfaces such as roofs and pavement that do not let rain soak into the ground.
Stormwater bed
An underground storage area that holds rainwater and releases it slowly to reduce flooding.
Land development
The township's formal review of new buildings and site changes before construction.
Modular classrooms
Temporary prefabricated classroom buildings used while permanent space is built.

Researched by AI from public sources on Nov 1, 2026. It can make mistakes, so check the linked sources and the municipality before relying on it.

Scope estimate for contractors

Estimated construction value: $6.6M